Sanitary sewer replacement and improvement
Carlis Place. Project# 20-2300D2 and 20-1310B
The Region of Peel will be working in your area to replace the sanitary sewer and services at the Carlis Place, as shown on the attached map. Sanitary sewers are underground pipes that carry wastewater from your home/business to a wastewater treatment plant. Wastewater is created when water goes down the drain or is flushed down the toilet. As pipes age and our population grows, we need to replace older sewers to keep providing you with high quality wastewater services
Construction schedule
Construction is planned to begin in July 2022 and be completed in August 2022.
All work is under warranty for two years from the completion date.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices at peelregion.ca/construction.
Contractor and working hours
The work will be completed by Trisan Construction and supported by IBI Group, both under contract to the Region of Peel. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your area to be under construction for a longer period of time.
Traffic and parking
We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.
Areas impacted by construction
Replacing sanitary sewers usually require digging a trench within the municipal right-of-way. This trench might cause temporary damage to roads, curbs, sidewalks, boulevards, driveway aprons, and lawns within the municipal right-of-way.
In addition, depending on its condition, the Region of Peel may also repair or replace the municipal portion of the sanitary sewer connection, the smaller underground pipe running from your home or business to the Regional sanitary sewer system. This may require digging up either the lawn or driveway above this section of pipe and disturbing an area at least 2 square meters. Any damage caused by Regional construction will be repaired. We recommend you delay any driveway paving or major landscaping projects until this construction work is completed.
In-ground sprinkler systems
As the front lawn may be affected by this construction work, we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.
Tree trimming
If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.
If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.
Repairing areas impacted by construction
We will start repairing the impacted road, curb, sidewalk, driveways, and lawns (if any) once the new sanitary sewer is buried and work has been completed on all sanitary sewer connections on your street. Repairs may be delayed due to contractor availability or certain seasonal weather conditions.
For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3°C.
- Asphalt is not available in large volumes during the winter. Asphalt usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available beginning in late May. We will replace the sod on your property once it is available. We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Repairing grassy areas
The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.
Driveway access
It may be necessary to block your driveway for a short time when crews are digging the trench for the sanitary sewer, working on your sanitary sewer connection, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. Whenever possible, we will work to ensure businesses can be accessed. Please contact us if you have special needs related to access.
Repairing driveways
- Asphalt driveways: If we need to cut a section of your driveway, the driveway will be repaired by paving a stripe over the disturbed area, resulting in minimal seams in the final driveway. The Region of Peel cannot replace your entire driveway. If you would like to have the rest of your driveway paved, please contact the contractor, Trisan Construction, 416-410-3839.?The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of the Region of Peel.
- Interlock or concrete driveways: If we damaged a portion of your driveway, our contractor will reinstate the damaged portion of the driveway.
Waste collection
If you receive waste collection from the Region of Peel, your garbage, recycling, and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.
Vibrations
You could feel slight vibrations from the construction work.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/construction/workzonesafety.
Keeping you informed
We will let you know if there are any major changes to the plans.
We value your feedback
After we have finished, we will invite you to provide feedback on the construction project.
You can sign up to receive this survey electronically at peelregion.ca/construction by clicking ‘Sign up for email notices’.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.
Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409