Queen Street sidewalk construction
From Bramalea Road to Central Park Drive (Southside), City of Brampton. Project 22-4141
We have finished the work. The project is under warranty until November 15, 2025.
What are we doing?
- The Region of Peel will be carrying out the construction of Queen Street Sidewalk from Bramalea Road to Central Park Drive (Southside). The work includes, but is not limited to:
- Hot mix asphalt paving.
- Grading works.
- Restoration and Minor related works.
Where?
- On Queen Street from Bramalea Road to Central Park Drive (Southside).
When?
- Start: week of October 10th, 2023
- Finish: November 30, 2023, weather permitting.
Who can you call?
Fusillo Paving Company Limited under contract to the Region of Peel |
||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Frank Fusillo Jr. | Project Manager | 416-717-1252 |
Frank Fusillo Sr. | Site Supervisor | 647-893-3089 |
Region of Peel | ||
Nabiel Matta | Project Manager | 905-791-7800 x 7862 |
Tapan Barua | Site Inspector | 647-330-9105 |
Working hours
- The Contractor’s normal day working hours are from 7:00a.m. to 7:00p.m, Monday to Friday. The Contractor will utilize this time to complete all major works.
- The Contractor is also permitted to work on Saturdays, as may be required from 9:00a.m. to 3:30p.m.
- These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic control
- Existing traffic flows will be maintained during construction. However, traffic lanes will be temporarily reduced during construction.
- Emergency access will be maintained at all times.
- Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
- Use caution when travelling through the work zone.
Driveway access
- We anticipate that driveway accesses will be maintained.
- If we need to block your driveway for a short time, you will be contacted to arrange for the best time and for alternate access, if available.
- If you have specific access-related requirements, kindly contact the Project Manager
Project updates
- The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
- We are committed to ensuring minimum disruption to your homes and businesses.
- Please call the Project Manager or Inspector if you have any special needs.
Who can you contact?
Nabiel Matta,
Project Manager
Region of Peel
905-791-7800 ext. 7862