The Region of Peel has been working in your area to replace the watermain and water services along Murray Street. This work is required to maintain and improve the quality of your water supply.

At this stage in the project the new watermain has been successfully installed, leaving only the water services component to be completed. Water services transfer water from the new watermain to each individual property.

Water service construction is expected to begin the week of January 8, 2024. A temporary road closure (similar to what was in place earlier this year) will be required to complete this work.

Traffic impacts

We apologize for any delays or inconvenience resulting from these traffic impacts.

Keeping you informed

Weather and other unpredictable events may change the date of these traffic impacts. Receive timely project updates right to your inbox by signing up for e-notices. Visit peelregion.ca/construction/signup.

Information on this construction project can also be found at https://www.peelregion.ca/pw/construction/bram/20-1340D.asp.

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.