Removal of trees and fencing
8373 and 8387 Mayfield Road - Project 16-1177
Work to be done
- As part of the watermain construction on Mayfield Road, trees and fencing located in front of your property will be removed within the Region’s widened right-of-way and disposed of, as per the attached sketch.
- If you wish to keep any of the fencing materials, gates, and light standards for later re-installation by yourself, please let us know as soon as possible.
Schedule
- This work is expected to occur from Wednesday, February 23 to Friday, February 25.
Who can you call?
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Melvin Gonzalez | Project Manager | 289-541-5777 |
Abhijeet Basi | Regional Construction Inspector | 647-824-9684 |
GMBP Consultants | ||
Contact Person | Responsibilities | Telephone Number |
Zoltan Tako | Contract Administrator | 519-501-4161 |
Eric McLennan | Lead Construction Inspector | 226-821-4064 |
Pacific Paving Limited Pacific Paving Limited will do the work, under contract to the Region of Peel |
||
Contact Person | Responsibilities | Telephone Number |
Dino Marchioni | Project Lead | 905-670-7730 |
Danny Jennings | General Site Superintendent | 416-318-9015 |
Construction statement regarding COVID-19
Construction is an essential service. We’re keeping employees, contractors and the community safe by complying with provincial regulations, physical distancing, using personal protective equipment, and adjusting work schedules and shifts.