Project 22-1340 B2

Watermain replacement and improvement

Torbram Road Between Balmoral Drive to East Drive
Heart Lake Road between Clark Boulevard and Orenda Drive
Elgin Drive between McLaughlin Road and McMurchy Avenue

Peel Region will be working in your area to replace the watermain and sanitary sewers along Torbram Road, Heart Lake Road, and Elgin Drive as shown on the attached maps.

As pipes age and our population grows, we need to replace older watermains and sewers to keep providing you

Construction schedule

This construction work will be completed one street at a time, and will begin on Torbram Road the week of March 25th, 2024. Once the underground work is completed on each street, we will begin repairing any driveways, boulevards, sod (grass), roads, curbs, and sidewalks impacted by our construction work. We expect construction on this street, including the associated repair work, to be completed by the middle of 2024. These timelines are estimates, as weather and other unexpected events may impact our timelines.
All work is under warranty for two years from the completion date.

Sign up for email notices

Receive timely project updates right to your inbox by signing up for e-notices.

Contractor and working hours

The work will be completed by Earth Boring Co. Limited and supported by consultant Associated Engineering (Ont.) Ltd., both under contract to Peel Region. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality's bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood/area to be under construction for a longer period of time.

Traffic and parking

We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.

Interrupting your water supply

We anticipate that this construction project will require temporarily shutting off your water.

For residents:

Areas impacted by construction

Installing watermains usually requires digging a trench within the municipal right-of-way, which includes the street and the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside, on the property line between your home and the road.) Depending on the location of the watermain , this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, lawns, and the bottom of driveways within the municipal right-of-way.

We therefore recommend that you delay any driveway paving or major landscaping projects until this construction work is completed. Any damage caused by Peel Region’s construction will be repaired.

In-ground sprinkler systems

As the front lawn may be affected by this construction work, if you have an in-ground sprinkler system we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can't relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.

Tree trimming

If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand. If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.

Repairing areas impacted by construction

We will start repairing the road, curb, sidewalk, driveways, and lawns once the new watermain is buried and new water service pipes have been connected to all properties on your street. Repairs may be delayed due to contractor availability or certain seasonal weather conditions.

For example:

Repairing grassy areas

The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer 'deep root watering' works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.

Repairing driveways

Driveway access

It may be necessary to block your driveway for a short time when crews are digging the trench for the watermain, replacing your water service box and pipe, or completing other construction activities. Please contact us if you have special needs related to access.

Waste collection

If you receive waste collection from Peel Region, your garbage, recycling, and organics will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.

Vibrations

You could feel slight vibrations from the construction work.

Optional protection plans for your exterior water pipes, wastewater pipes, and in-home plumbing

Many homeowners are not aware that they are responsible for maintaining the water and wastewater pipes both inside their home and outdoors up to the property line. If one of these pipes breaks, it can cause unexpected and costly repairs. Peel Region has partnered with Service Line Warranties of Canada (SLWC) to offer homeowners optional, affordable protection from unexpected home repairs. Learn more about the protection plans at plansforpeel.ca

Safety during construction

Construction zones require extra caution to keep everyone safe - pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visitpeelregion.ca/workzonesafety

Keeping you informed

We will let you know if there are any major changes to the plans.

We value your feedback

After we have finished, we will invite you to provide feedback on the construction project.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.

Water Linear Engineering
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409