Watermain and wastewater main replacement and improvement
Various streets within the M-Block
Project Updates
- We have finished the work. The project is under warranty until December 2019.
- June 2017: Lane Restriction and Road Closure Massey Street at North Park (PDF)
- May 2017: Watermain and Sanitary Sewer Replacement Madrid Crescent (PDF)
- November 2016: Construction Commencing on Madrid Crescent (PDF)
- November 2016: Restoration on Markham, Manorcrest, Montcalm, Marlow (PDF)
- September 2016: Road Closure Manorcrest Street (PDF, 272KB)
- July 2016: Restoration (PDF)
- June 2016: Road Closure Manorcrest Street (PDF)
- June 2016: Lane Restrictions and Road Closure at North Park Drive Extension (PDF)
- May 2016: Lane Restrictions and Road Closure at North Park Drive (PDF)
- May 2016: Madrid Crescent South Entrance Road Closure (PDF)
What we are doing
- Replacing and improving the aging watermain and wastewater main on the following streets.View area map (PDF):
- Manorcrest Street
- Marlow Place
- Madrid Crescent
- Montcalm Place
- Markham Street
- Replacing the water service pipe and sanitary laterals to property line.
Why
- To upgrade the water and wastewater system capacity and reliability as part of the Region of Peel's State of Good Repair program.
When
- We expect to start work on or about Thursday April 21, 2016, with a construction crew starting at the intersection of Manorcrest Street and Montcalm Place. Simultaneously, a second crew shall commence work on Markham Street to expedite the construction.
- The project should be completed before the end of June 2017. All work is under warranty for two years from the date of completion.
- We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.
Who you can call
Region of Peel |
||
Contact Person |
Responsibilities |
Telephone Number |
---|---|---|
Melvin Gonzalez | Project Manager | 905-791-7800, ext. 5042 |
Tom Graovac |
Inspector |
905-791-7800, ext. 3246 |
London Excavators and Trucking Ltd. |
||
Massimo Sansone |
Project Manager |
416-247-6601 |
Frank Carelli |
Supervisor |
647-926-9201 |
Working hours
- Our contractor's normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality's bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic and parking control
- We may need to reduce traffic to a single lane during construction.
- If we have to reroute traffic, we will place signs giving directions.
- On-street parking will be reduced during construction.
Driveway access
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
- Please call the Project Manager if you have special needs related to access or business hours.
Irrigation or sprinkler systems
- Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
- You may wish to move the sprinkler lines to inside your private property to avoid damage.
Trimming trees
- If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
- If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
- The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.
Interrupting your water supply
- It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water. Occasionally, we may have to reduce this notice to 24 hours.
- If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.
Vibrations
- You may feel slight vibrations from the construction work.
Replacing and taking care of your sod
- The contractor will take care of any sod we replace for 30 days.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
Repairing your driveway
- If we need to cut your driveway to replace the existing service valve or access the watermain, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately the Regioncannotcompletely replace your driveway.
- Several weeks before the driveway restoration work, we will send you an update with contact information for the contractor, in case you wish to have the remainder of your driveway (private side) paved at the same time.
- If you have any concerns, please call the Project Manager.
- We will repair your driveway as soon as we can, but there may be a short delay.
Repairing the road, curbs, and sidewalks
- We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
- We will complete the restoration on a street-by-street basis.
- Trenches on all streets shall be restored with asphalt to the existing road surface.
- As part of the overall improvement for the M-Block, the City of Brampton shall pave these streets as part of their road resurfacing program upon the expiry of the Region's warranty period.
Project updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any concerns or special needs.